As part of the project for the development of the Krasnoyarsk heat supply system included in the Yeniseiskaya Sibir KIP, two new boilers are being prepared for launch at the Krasnoyarsk CHPP-1. Now the boilers are being prepared for testing: This is the final stage before putting the equipment into operation.
Like other units, the new equipment is equipped with silencers that suppress the sound from their kindling, and modern electric filters with an efficiency of cleaning solid particles over 99%. In addition, a fuel-free ignition system will be used on the new boilers.
Also, the construction of new electric filters continues at CHP-1: to date, 11 out of 15 pieces of equipment have been put into operation. Work is underway to install foundations for the next electric filter at the site of the dismantled old gas cleaning plant. According to the environmental modernization program, such filters will replace the existing environmental protection equipment at Krasnoyarsk CHPP-1.
The total investment in the renovation of the Krasnoyarsk CHP-1 will amount to 22 billion rubles. SGK plans to complete the modernization of the station by early 2025. As a result, the emissions of CHP-1 will be reduced by more than 20%.
Recall that the project for the development of the Krasnoyarsk heat supply system involves a comprehensive environmental modernization and expansion of the Krasnoyarsk CHP-1, as well as an increase in the capacity of the Krasnoyarsk CHP-3.