The power engineers of the Siberian Generating Company (SGC), under the supervision of specialists from equipment manufacturers, are carrying out commissioning work on the steam boiler and turbine unit of the second power unit of the Krasnoyarsk CHPP–3 under construction. The facility is being prepared for testing, the final stage before operation begins.