At the St. Petersburg International Economic Forum, Mikhail Kotyukov, Governor of the Krasnoyarsk Territory, held a meeting with Musa Bazhaev, President of Alliance Group JSC, and Ahmed Bazhaev, CEO of Chernogorskaya GRK LLC. The meeting participants discussed the progress of the construction of the Montenegrin Mining and Processing Plant.
Currently, the facility is 80% ready. The installation of the main technological equipment is being completed, and electrical and engineering systems are being tested. The main construction and installation works have been completed
A quarry has been put into operation on the main gas pipeline. Mining operations have been underway at the facility since February, and in November the company plans to start mining copper-nickel ore and ship the first concentrate.
The project to develop the world's largest platinum-palladium deposit is included in the Yenisei Siberia integrated investment project. With the assistance of the Yenisei Siberia Development Corporation, an agreement on the protection and promotion of investments was concluded between the investor and the Ministry of Economic Development of Russia.
The development of the reserves of the Chernogorskoye field is the first stage of the project to create a new mining and metallurgical complex in the Norilsk Industrial district. At the second stage, the reserves of the southern part of the Norilsk-1 field will be involved in the development.