Increasing the ore processing capacity of the gold recovery plant

Save to Favorites
Add materials that are important to you to your favorites in your Personal Account

For this Log in or go through the simple one Registration
Investor:
Vasilyevsky Mine JSC
Implementation period:
2019 – 2025 years
Investment size:
7.0 billion rubles .
Implementation stage:
Implemented

The aim of the project is to increase the ore processing capacity of the Vasilyevsky Mine gold extraction plant from 413 thousand tons to 1000 thousand tons and increase the raw material base. As part of the project, it is planned to reconstruct the ZIF and relocate residents of the village of Partizansk in accordance with the Law of the Krasnoyarsk Territory dated 10.03.2016 No. 10-4274 "On social support for citizens relocating from the village of Partizansk in the Motyginsky district of the Krasnoyarsk Territory" (more than 400 people). 


The creation of a new production facility will provide about 250 new jobs